Lot 42 - insulation finished, drywall soon to be stocked inside home. No issues found Lot 43 - drywall still in progress, tapers inside. Flatwork setup for inspection. No issues found. Lot 44 - foundation still in progress, waiting for inspection. No issues found Lot 45 - rough plumbing being installed. Window guard rails in, and windows are getting installed soon. No issues found Lot 3 - backfill in progress. No issues found Lot 4 - foundation in progress. Forms being setup. Lot 6 - framing post and beam, tall post and beam requiring scaffolding and ladders, PPE worn, no issues found. Lot 8 - framing all complete. Window guard rails are in. Reminding framers to stack lumber neatly for returns. Inside and around clean. No issues found.