Painter is in lot 151 all PPE\'s accounted for Lot 153 and 152 cabinet guy has Guard on saw and is staying safe also there is vacuums attached to his equipment Lot 194 and 193 cabinet installers are in there and all PPE\'s accounted for Lot 192 floor installers were using a planer on the floor and staying safe doing so Lot 191 tile and backsplash was going in, tile installer was using a mask while mixing material No framers were on site No, Excavation was being performed Lots 148 through 150 landscapers had all reflective vests on and we\'re staying safe while unloading heavy rock Also, all extension cords had grounding pens