Lot 3 - driveway and porch prepped for concrete, waiting to pour no contractors on site, no issues found Lot 4 - foundation poured hardhats worn with overhead pump used to pump concrete. No issues found Lot 6 - framing in progress, standing first floor walls, lumber organized safely on site, good housekeeping, PPE worn, no issues found Lot 8 - framing complete, guard failed in windows for safety, housekeeping good, siders starting to setup pump jacks for installing paper around house. No issues found Lot 44 - foundation still in progress, no contractor on site, waiting for inspection approval to pour. No issues found Lot 45 - electrical rough starting, ladders used properly for higher areas in garage, no issues found Lot 10 - excavation was just complete, stock piles secured, hay spread for erosion control, no open trenches, waiting for foundation to begin, no issues found