Just to let you know, not many trades are out here today due to holidays coming up. Lott 192 has millwork guy and tile guy in there. Tile guy is using mask and using water when cutting concrete materials and millwork guy has glasses on and is cutting with a guard on his saw everyone\'s being safe. Lot 148 wire shelving and mirrors and bath accessories install is happening and PPE is being worn . Lot 223 through 226 framers are working. All hardhats are being worn ladders are set up at proper angles and eye protection is also being worn. 215 through 218 roofing is being installed tiedowns are being worn eye protection, being worn people are being safe And the only foundation we have out here the rebar is capped and there\'s no penetration hazards.