Lot 118. Rough plumbing in progress. Ladder used by plumbers observed as OK. Garage concrete slab being poured. Workers using proper gear to complete concrete finish. No other issues. Lot 119. Post and beam framing in progress. All personal protective equipment being used. Skil saw guards properly used. Nail guns properly used. No other issues. Lot 120. Garage concrete slab be poured. Worker is using proper gear to complete concrete finish. Cider installing Tyvek building wrap. Ladder use as observed was proper. No other issues. Lot seven. Electrician rough wiring house. Ladder use proper. Tool use proper. Electric cords in good condition. No other issues. Lot 11. Lot being excavated for foundation. Spoils are being stacked appropriately 2 feet from location of where foundation will be formed. No other issues. Lot 12. Lot being excavated for foundation. Spoils are being stacked appropriately 2 feet from location of where foundation will be formed. No other issues.