Lot 44 underground piping being installed, water, sewer, rain drains. Excavators working around digging ditches and laying pipe. No issues found. Lot 45 siders completing siding, pump jacks setup properly, PPE worn. No work inside the home, house is waiting for inspections prior to insulation start. No issues found. Lot 3 framing first floor, standing walls. PPE worn. No issues found. Lot 4 excavator backfilling around house. No issues found. Lot 6 framing complete, roofing completed, windows installed, house drying out and getting ready for plumbing rough to start. No contractors on site. No issues found. Lot 8 electricians finishing up rough-in. Back deck being installed. Guardrails setup at back deck. No issues found. Lot 10 foundation poured. Waterproofing installed around foundation walls. No contractors on site. No issues found. Lot 11 foundation forms setting up. PPE worn by foundation crew while cutting rebar. No issues found. Lot 33 excavation in progress, trucks loaded and hauling off dirt. No issues found.