Lot 117. First floor framing in progress. Waiting on second floor material to be delivered. There are no issues. Lot 119. First floor framing in progress. Waiting on second floor material to be delivered. There are no issues. Lot 118. Electrician starting rough installation. Ladder use is proper. Eye protection being used while operating tools. Electric cords are in good condition. No other issues. Lot 120. Rough HVAC in process. Ladder use is proper. Electric cords are in good condition. No other issues. Lot eight. Siding in progress. Scaffold use safe and proper. Ladder use proper. Eye protection being used. Vacuum being used while cutting in siding. No other issues. Lot 11. Concrete foundation being poured. Hard hats being worn by all involved. PPE being worn. No other issues. Lot 12. Concrete foundation being poured. Hardhats being worn by all involved. PPE being worn. No other issues. Lot 78. Concrete foundation being poured. Hardhats being worn by all involved. PPE being worn. No other issues.