Lot 3 - framing finishing up. Asked framer to put back guard rail at back patio deck framing and to clean up around jobsite. Lot 4 - deck framing currently, about to stand up first floor walls today. Framers all wearing PPE. No issues found. Lot 5 - excavation about to start. No issues found. Lot 6 - jobsite need cleaned more. All windows installed. No fall hazards or guard railed needed anymore. Deck almost completed. No issues found Lot 7 - excavator just finished this morning, ready for foundation forms. No ditches open. No issues found. Lot 8 - insulation being installed. Crew wearing PPE while using pneumatic stapler to install bibs and blow-in insulation. Sider pump jacks being removed, siding complete. No issues found. Lot 10 - underground pipe work installed. Inspections today. Stockpiles kept away from open ditches. No issues found. Lot 11 - foundation complete. Waiting for waterproofing. No contractors on site. No issues found. Lot 44 - almost ready for framing, all backfill is done and erosion BMP\'s in place. The garage flatwork and patio and porch is setup for concrete. Pouring today. No issues found.