PVv 476-477-478-479: framing crew is working on site. Safety rails are installed second floor. Half of the exterior walls are up and safety rails are up on windows. Some of the safety rails have been removed and are on the ground in the alleyway. I had a crew stop and disassemble all the safety rails as some of them had nails sticking up peep, it would\'ve been a hazard. I also talked about wearing safety glasses. One of the crewmembers did not have safety glasses on our hats are on the rest of PPE is on I talk to the crew about making sure the courts and hoses or stowed in a way that allows them to work without getting tangled. I also had them stop and tidy lumber stack lumber and clean up all debris into three piles. And place them in the trash bins and then stop and stack all wood garbage into the piles X on the exterior. When I left the job site was in excellent condition. GFCI\'s were used as well. Also saw guards were in tact and size were in good working order.. PVV 480=481+482-483: foundation crew was working on these units, setting up forms and tying rebar. Their cords were good and using GFCIs. Their saws were operating safely and played cards were intact. The crew was using good PPE and dressed appropriately. PVV 690 the siding crew is working on this house on the left side and both installers are tied off. The second guy is tied off to his own tiedown location on the upper gable. Cords are in good condition. GFCI used is three-way and in good condition. Hoses and cords are tidy and neat, the scaffolding is set up correctly with base plates and level in Plumb. Hi viz. ability. Vests are use on hardhats glasses are all worn. Period. The guy on the ground cutting is using the vacuum cleaner and mask as well and all of the workers are using good work attire and proper appropriate safety.. PVV 701 framing, crews are assembling first floor walls. All the framing crew is wearing high, viz. ability, sweatshirts, and vests. All framing crewmembers have hardhats and everyone of them put on safety glasses when asked. The chords are in good condition. GFCI is in good condition, and cords and hoses are stowed and placed appropriately for safe walking. Cordless saws are being used and they are all in good condition with the guards intact. PVV 676 roofing contractor is that replacing shingles tied off and ladder is tied off extending 3 feet be on the roof and the worker is working safely. All appropriate PPE is being worn and a visibility sweat shirt is being worn.. PVV 683 integrity roofing has an installer on site. The ladder is tied off and set up appropriately. And the installer is wearing appropriate PPE. All of the equipment and seems to be in good working order. The GFCI is plugged in for the compressor. PVV lot 680 : taping crew is here and working off 6 foot ladders. Working safely at this time applying second coat. PVV lot 67 912 foot scaffolding assembled and I made sure the workers had the scaffolding railings up and when they were in here installing mud and taping and topping .