Lot 160 electricians working inside rough in Safety glasses being worn, correct ladders being used no issues Lot 161 started framing, second floor, hardhats and safety glasses being worn. Spoke with them about making sure they build the stairs before framing second floor. They told me they would. I will keep an eye on them. Lot 176 installing floor joist for second floor hardhats being worn safety glasses being worn, proper ladders being used safety rails are up. I spoke with foreman and told him to make sure the stairs are built before they start framing the walls. 177 flat work being poured in garage and patios, using a line pump no overhead hazards. Lot 178 foundation dig out, locates were completed before dig out no issues. All garbage was picked up yesterday. Site is in clean shape.