185 framers working on first floor walls, site is good. 198 fire sprinklers being tested, side is good. 222 drywall taping, site is good. 223 no workers, site is good. 224 flatworkers setting up concrete forms, site is good. 236 foundation forming, site is good. 237 foundation crew stripping forms, site is good. 238 insulation being installed, site is good. 239 electric wiring and siding being installed, site is good.