Rolling Meadows Homes under construction: Lots 88-92, 77, 62-66 Trades on- site: Villalobos Framing @ 66 Siding works @ 90 Western window installers @ 91 Westside Drywall @ 65 Westside Insulation @ 90 Lot 90 siders not having safety glasses or vacuum for cutting. Talked to crew told them to wear safety glasses and to pull out there vacuum @ 8:30am Lot 63 temp stair rail was removed, called Framer to send crew over to reinstall @ 8:36am Lot 64 missing 2 window braces, called framer told home to send crew over to install @ 8:36am Lot 66 framers running power cord across the street unprotected, called framer told him to have crew have cords protected @ 8:40am